Project Overview

A 85kW solar mini-grid powering over 300 households, two schools, and a primary health center in Gidan Kwano community. The project includes training for local technicians and a pay-as-you-go system for affordability.

Project Timeline

  • Mar 2023 Project kickoff and community engagement
  • May 2023 Site survey and design completed
  • Jul 2023 Equipment procurement and delivery
  • Sep 2023 Installation of solar panels and batteries
  • Jan 2024 First phase commissioning (50 households)

Key Details

Start Date 01 Mar 2023
End Date / Expected 31 Aug 2024
Project Manager Engr. Musa Aliyu
Contact Email musa.aliyu@sesn.ng

Partners & Sponsors

REA GIZ Niger State Government